Performance and commissioning experience of new te-cyc™ plant at Hawkhurst South WwTW: PRESENTATION ONLY
Ben Hazard, Process Engineer, Te-Tech Process Solutions, UK
Connor Sandalls, Process Engineer, Southern Water, UK
(free)
Process Commissioning
- The te-cycTM plant was commissioned with the new Low TP permit already in force
- Initial commissioning undertaken in winter / higher flow period
- Biological load currently accepted by the plant is less than Design load.
- Site is currently treating an FFT of 11 l/s, with the future FFT of 15.8 l/s being implemented soon
- te-cycTM designed to treat future FFT (15.8 l/s) and will be receiving these flows subject to completion of hydraulic modifications to inlet works